Staff analysis report

What do the columns productivity and utilisation represent?  They appear to be percentages, but of what?

  • 0
    Suggested

    Hi Gayle,

    Thanks for your post.

    The utilization and productivity is....  

    The amount of billable hours for the period you are running the report for / how many working hours the staff member is set up for x 100 

    Example 1: Running the report for a week, employee works 35 hours a week and has billed 5 hours 

    5 hours logged / 35 hours working period  x 100 = 71.43

    Example 2: Running the report for a single day, employee works 35 hours a week and has billed 5 hours 

    5 hours logged / 7 hour working period x 100 = 14.29 

    Often the productivity will be the same but it can differ if they staff member logs hours for non-billable work.

    If this helps, please click Verify Answer.

    Regards,

    Andy
    Sage UKI