Production Management / Work Ticket Entry - Budget Direct Costs

Where can I populate original budget dollars for Direct Costs in Work Ticket Entry?

Sage 100 v 2024 sp1

Thanks in advance:)

  • 0

    According to HELP,

    • BUDGET Direct Cost: This field always displays zero.

    • CURRENT Direct Cost: This field displays the total transaction amount of Accounts Payable direct cost transactions. This value includes overhead costs calculated from Account Payable invoices and manual checks assigned to work ticket steps.

    It appears the program is not designed to enter a Direct Cost Budget.  You can submit this as an enhancement request on the IDEAS site.