Maintain Projected Demands - IRP Module SAGE 100 2024

I was able to use the above in MRP very successfully but really struggle with the IRP version.  Part of this is due to the fact that it considers warehouses SEPARATELY instead of grouping them into a nice total using the MRP Warehouse Grouping Function.

At any rate, can someone tell me how I know what warehouse I should set up the Projected Demand for in order for the exploded BOM's to accurately reflect needed components?   Note that the end/sold items have different default warehouses but ALL COMPONENTS are ordered and purchased from the Main Warehouse 000.  I just want to be able to look at warehouse 000 for the printed version of my IRP report for purchased parts.   That is all I care about at the moment.

So should the projected demand(s) for our end items be set up under the warehouse code that is the default for that item?  Or should I just set up the projected demand under 000 for everything?

I am really confused by the "separation" of warehouses and how it impacts the IRP output.    This is something that was much more straightforward in MRP.

(Note too that all of my reorder points for components are set up under the Main Warehouse 000.)

Appreciate input from anyone who has successfully conquered IRP output...!

Parents
  • 0

    FYI, IRP Warehouse Grouping is on the roadmap to be included in a future release, however, it will not be the upcoming 2025 release.

    Have you discussed this with a Sage partner?  There are a lot of questions to ask.  For instance,  If components are in a different warehouse you won't be able to use the 'Create P/O' or 'Create W/T' feature if you enter Projected Demand in the Finished Good warehouse.   It will create W/T's and P/O's when you actually have quantity on hand the warehouse 000.

Reply
  • 0

    FYI, IRP Warehouse Grouping is on the roadmap to be included in a future release, however, it will not be the upcoming 2025 release.

    Have you discussed this with a Sage partner?  There are a lot of questions to ask.  For instance,  If components are in a different warehouse you won't be able to use the 'Create P/O' or 'Create W/T' feature if you enter Projected Demand in the Finished Good warehouse.   It will create W/T's and P/O's when you actually have quantity on hand the warehouse 000.

Children
  • 0 in reply to ksmcwhir

    I have tried to ask these questions with our partner but haven't received very satisfactory responses.     For what it's worth, we have no intention of using the "Create PO" or "Create WT" functionality.    We will continue to do these manually.     I just want to know how to set things up so that it works just like the MRP report used to with the "Required Action" summary level option.   It worked beautifully for us and I cannot figure out how to get the same sort of output with IRP.     Frustrating.

  • 0 in reply to Jeanne Ploshay

    I suggest you create a support ticket with Sage support so someone can get live connected to see if the reporting functionality you are looking for is in the product.