Hi,
Is there a way to get Sage to give a warning before closing a work order if not all the parts are issued to it. I had a situation today where a ton of work tickets were turned in and one should have been completed and closed before another to create a backfill to go to a top level (the top level was cut with all the sub-assembly work orders - done by a previous worker) and all turned in at the same time, but I completed and closed the top level before the sub-assembly, so the top level WO had a part not issued to it. It would have been nice to get a warning that not all the parts had been issued before closing.
Anything like that?
Thanks.