Editing our "Approval Sheet" Which Field for Totals?

Suggested

Hello We have an approval sheet that was created for us for billing to show the guys total labour and costs on it. However it does not total the costs, so for quoted jobs we would have to tally the costs ourselves - for T+M billing through Work Orders/Invoices/Credits module in 11-2 - is there a field I can enter under Part Order and Cost that would total each column and/or even better if I could get a field to total both columns? 

This was one big plus of our old system, their approval sheets and billing process was awesome as it protected the payroll time (couldn't just remove from a work order) and would pull in labour, PO's and parts into the billing and then on one approval sheet shows you all of this data pulled in for costing etc. This is why we had this created however it needs modification so we can see totals. 

  • 0
    Suggested

    Good morning Pam

    Our T&M module is not connected to the service module, it is a billing module for jobs in 3-10.  That being said, you can probably create calculated fields to pull the values by cost type is you make that field/column mandatory.  Then you could group and sub-total by cost type.

             

  • 0 in reply to Char DeLange

    Hi Char, Ok thank you I will try this. We use the 11-2 module for all our billing whether quotes or time and material through service billing. 

  • 0 in reply to Pam Zmija
    Suggested

    Ok, but you will find the 3-10 module is much better for any T&M work.

  • 0 in reply to Char DeLange

    We need to be able to use the dispatch scheduler to schedule our guys and also be able to enter in specific info. From what I am seeing in T&M module, its very basic. We need to be able to itemize parts and labour used under a specific customer and also be able to put in a description. So the work orders way of doing T+M and Quoted jobs works much better. 

  • 0

    Hi Pam,

    Looking at your screenshot, this can be done in Report Writer. Your Subtotal 1 band already totals the invoice amount, so the cost totals can go in the same place:

    - Add the Part Order and Cost fields to the Subtotal 1 band, set to total, so each column sums for the work order

    - Add a calculated field next to them that adds the two together for a grand cost total

    - Your labour line (the second Detail band) only shows Actual Hours right now, so if you want labour cost included, a cost field needs to be added to that line first

    Then it works the same for quoted and T&M work orders, with no tallying by hand.

    I'm a consultant and do this kind of report work. If you'd like me to make the changes for you, or help with anything else since the move to Sage, send me a message.