When trying to export change order to job cost from sage estimating to sage 100,
I keep getting an error message stating a category must be provided
What am I missing here?
We are just getting started on Sage Estimating. Is there a way to save multiple copies of takeoff revisions for the same job. So you would have your starting takeoff. Then after reviewing and maybe making some design changes you created and second takeoff…
I want to calculate against the previous section subtotal, not the running total subtotal. I should not have to go outside Sage to perform this calculation. I know I can apply percentages to other individual addons but not a subtotal of a section addons…
Ever since we updated to version 23 we have been having issues with the addons that are already saved in the DB being asked to save again (duplicating) when saving the template. If we save these addons it creates new entries with new addons numbers. When…
Once a sub is assigned to a line item I am getting this error if I try to make any changes to Description or qty: "The item belongs to a bid grid with a selected subcontractor. To make the changes to the item switch to self perform"
This changed in…
I am using the means integrator, how do I get the estimate to show hours for the tasks? Example: the estimate says the item will cost $6.35/cy how do i get it to show how many cubic yards per hour without doing a bunch of converting? I add all the tasks…
I'm wondering how labor productivity interacts with crews. If i change my crew from two resources to three, do i have to adjust my labor productivity to account for those added resources?
I'd like my labor productivity to be calculated per "resources…
Is there any way to setup an addon for it to be a 'percent of total'
Context:
I want to be able to add a margin instead of a markup. So i'd like my profit to be 10% of my total instead of adding 10% to the current total.