Hi guys! First post here :)
I'm having trouble understanding what to do when inputting an invoice from the purchase order module.
The invoice that I received has 3 line items, 2 of which were in the purchase order. The third one is different. After talking with my colleague who raised the PO, he said that the company supplied us a wrong item. In the meantime I received another invoice referencing the same PO but with just the new item in it.
How do I manage this flow of information in sage? When receiving an invoice I always go in the purchase order module and click update. But in this case if I update the PO into the ledgers, Sage will select the three correct items, but I need to input the invoice as it is (with the wrong item in it)
I thought about going for it this way: select the po, update to ledgers. In the following window I'll edit the item we didn't received and select a quantity of 0. Then in the following batch update window I'll add a new row with the description of the wrong item and then click update. Later I'll input the invoice for the correct item and the following credit note.
Is this the right way to tackle this issue?
Sorry for my english, I hope everything is clear enough :)