I have set my inventory up as FIFO, however, I was wondering if there was a way to allocate an inventory purchase direct to a project while tracking the inventory too. Our business is project base and it is not the most accurate exactly to arrange by FIFO.

Example: I have a project needing 500 widget, but I only have 300 in stock. FIFO will say that I will ship 300 old widgets and 200 new widgets. In reality, I will just order 500 new widgets and send them all to the project. However these new 500widgets might cost more then the 300 old ones and my project/inventory costing will be out.

  • 0
    I don't think there is any way to force Sage 50 to do this, sorry, without adjusting all your current 300 inventory out, receiving the 500 new inventory, selling the new 500 inventory, then adjusting the current 300 inventory back in again.

    This may be just my opinion but if your business is truly project-based, you would not have any inventory in stock, so it would not be an issue. However, you do have inventory and decided at some point it should be FIFO-based so it is doing what you asked of it.
  • 0
    If you use Sage 50 Quantum, and use Locations (warehouses), you can use a separate 'warehouse' for Projects.

    Sage 50 Quantum Edition, formerly known as 'Simply Accounting Enterprise Edition') keeps separate inventory cost ledgers for each 'Location'.

    (I wouldn't use more than a couple dozen warehouse / Locations in Sage 50, definitely don't set up a separate Location for each Project unless you only do a few each year, close them out at the end, then mark them 'inactive'.)