task scheduler 4.5 SQL

I've run into a situation where any automated task we put on the task scheduler will run, but not end, leaving orphaned tasks out there.  I have to manually kill the process by PID.  Does anyone know of a fix?

 

Thanks,

Andrew

 

Parents
  • And over 10 years later I'm having the same problem with Sage 100c Advanced 2018.  We are upgrading over the summer, but I'd really like to get Task Scheduler working.  Did anyone ever find a fix to the orphaned tasks?

  • in reply to renrut

    What kind of job?  We had issues chaining an auto-post job to the DTR (which we suspected was tied to Paperless issues, but we never proved that...), needing to put the DTR posting into a separate task.

Reply
  • in reply to renrut

    What kind of job?  We had issues chaining an auto-post job to the DTR (which we suspected was tied to Paperless issues, but we never proved that...), needing to put the DTR posting into a separate task.