We have a customer that receives grants on Projects and they are wanting to record the amount expected as an estimate, however a negative estimate value cannot be added. Would anyone have an idea how to apply this?
Thanks
We have a customer that receives grants on Projects and they are wanting to record the amount expected as an estimate, however a negative estimate value cannot be added. Would anyone have an idea how to apply this?
Thanks
You could create an item called GRANT or whatever you would like. Receipt it into inventory with negative cost, assign it as a resource. and then expense it to the contract under that project with material usage. As far as your GL structure goes those are decisions to make on your end.
You could create an item called GRANT or whatever you would like. Receipt it into inventory with negative cost, assign it as a resource. and then expense it to the contract under that project with material usage. As far as your GL structure goes those are decisions to make on your end.