Change order number digit limit

SUGGESTED

Is there a way to add allowable digits to the change order number field?

Thanks!

Parents Reply Children
  • 0 in reply to superaccountant
    The change order # field allows up to 8 digits. Any more would need to be submitted as an enhancement request as that is a change to the program itself.
    Why do you need more digits? If you need more you will need to use another field to expand that capability.
    In the past, I have changed how they print on the documents to include the job #, but you can't change the field itself.
    Sorry
  • 0 in reply to Char DeLange
    We enter the 5 digit job code then a dash and then a 3 digit change order.

    For prime changes we add 2 digits after the dash
    For sub changes we add 3 digits after the dash

    This was done so the owner doesn't see gaps in the change order sequence.

    Example:
    Change order 13100-01 (is the first prime change order)
    Change order 13100-500 (is the first sub change order) (problem here is we need 9 digits)
  • 0 in reply to superaccountant
    We also have the change order number field set to "unique" so we don't have duplicate numbers across the same job and across multiple jobs.
  • 0 in reply to superaccountant
    SUGGESTED
    OK I get it now.
    So as I stated before, you don't really have to include the job number in the change order number itself, but you can customize the change order forms to print the job # - change order number on them.

    What I have suggested over the years is to keep the customers change orders whole numbers like 1.0, 2.0, 3.0 but then internal/subchange orders become 1.1, 1.2, 1.3, until the customer goes to 2.0, then the sub changes to 2.1, 2.2, etc.
    And just to be clear the subcontractors have their own change order numbers as a separate column down in the grid.

    I just don't foresee Sage expanding that field for such a long number, but you can always submit an enhancement request.
  • 0 in reply to Char DeLange
    How would this work if we have the field set to "Unique number only"

    Each job would need it's own numbering system
  • 0 in reply to superaccountant
    I just tested in Sample Co and it appears you won't be able to use require unique if you want to track by job #.
    But the system does look to the job and phase and automatically selects the appropriate next change order # in whole numbers.
    In other words, if you phase your jobs, it will default to 1,2,3,4 within in phase of the job as well as tracking by job #.

    When entering change orders you could just do a lookup using F5 and sort by job # to verify the next number before you enter.