If using the Misc worksheets % complete what report(s) can be utilized to see the "Entered" percentages complete as opposed to the calculated?
If using the Misc worksheets % complete what report(s) can be utilized to see the "Entered" percentages complete as opposed to the calculated?
Hello John,
The JC Profit, JC Profit (as of Date), JC Profit Variance, JC Work in Progress report report all use the % Complete entered for the Job.
Knowledgebase article 45287 has attached a PJ Schedule of Work in Progress that also uses the % Complete entered for the JC Job.
These reports only capture "entered" percentages for job totals not individual cost code and/or category line items. There is a Labor Hours report PJ-Labor Hours that utilizes the % Complete by Cost Code or Category. What job cost reports will capture these entries by Cost Code?
I assume there is no way to do this at the category level?
The percentage complete can be entered at the category level, but there are no standard reports that report at that level. A custom report would be needed.
*Community Hub is the new name for Sage City