I'm trying to generate a report in Time Slips that will give me hours of each task recorded for a specific user for a specific client in a specific timeframe.  For example - A report showing the hours by task that user #1 recorded in the week ended May 8 for client A.  I'd like the report to easily show me that for client A - user #1 recorded 8 hours on task 1 (accounting), 20 hours on task 2 (consulting), and 12 hours on task 3 (tax) for a total of 40 hours for the specified period.

Parents
  • +1
    verified answer

    Yep, we can do that. But going to be a bit difficult to provide all of the steps here.

    I would do a Slip Listing report, filtered by date, user and client, sorted by task with a subtotal, and the option for only show subtotals and grand totals selected.

    Such a report would take me less than 6 minutes to set up.  Try it yourself, but if you'd rather just pay someone to do it, give me a call.

    Nancy Duhon, Esq.
    Duhon Technology Solutions, LLC
    Master Certified Consultant for Sage Timeslips
    Providing individual Consultations and Third Party Remote Desktop Support - including older/unsupported versions.
    404-325-9779
    [email protected]

  • 0 in reply to Nancy Duhon

    Thanks for the guidance.  I was able to modify the Slip Listing report settings and save the template and the report looks good.