Reports Project Hours vs Budgeted Hours

I am new to this Sage Forum...I have just started the last 3 months using Sage 100, however had 8 years with Sage 300.

I have been modifying some of the reports however, noticed there are several that can not be modified.  Some of these I would think would be basic to a construction software.

Are there any custom reports created for other customers posted somewhere on this site that a person could download and utilize.

I am looking for a Project Actual Hours vs Budgeted Hours Report by area / by cost code / capable of being summarized by Employee.  (With no $$ that I could sent to Proj Supers or Foremen)

Thanks

Ken

Parents
  • The only report I have found that gives actual to budget hours is 6-1-2-47 but it is part of the total job costing report. We had our consultant create a Crystal Report that lists the jobs in a single row with this info (along with other info). It seems like it should be a fairly easy report to create in the Queries but I have not yet created one.
  • in reply to Kathi from Santa Rita
    Thanks Kathi,
    I had looked at that one and it would have been great if it was modifiable allowing me to opened and edited collapsing the detail. I probably need to take a report-writing class as I am finding the canned reports quite cover the information in a format to disseminate to some of the Supers or Foremen.
Reply
  • in reply to Kathi from Santa Rita
    Thanks Kathi,
    I had looked at that one and it would have been great if it was modifiable allowing me to opened and edited collapsing the detail. I probably need to take a report-writing class as I am finding the canned reports quite cover the information in a format to disseminate to some of the Supers or Foremen.