Anyone know of which reports I can use in Project Management (6-1-2) that will include current payroll that has been computed but not posted? Or for that matter payroll record costs that are not final computed? Thank you.
Anyone know of which reports I can use in Project Management (6-1-2) that will include current payroll that has been computed but not posted? Or for that matter payroll record costs that are not final computed? Thank you.
I use report 6-1-12 for this. It is called a committed cost report
I use report 6-1-12 for this. It is called a committed cost report
Thank you!