Forecasting

SUGGESTED

Is there a way to forecast in Sage 100 Contractor?

Parents
  • 0
    SUGGESTED

    Have you looked at the Cost to Complete menus?  6-8-1, 2 or 3?  It is a tool to manipulate the % complete based on what you know to be true when your costs are lagging behind.  You do have to use the Options Update feature whenever you open the window to get the data to refresh, otherwise the budget, costs to date will be whatever you saw the last time you opened that job record.  

Reply
  • 0
    SUGGESTED

    Have you looked at the Cost to Complete menus?  6-8-1, 2 or 3?  It is a tool to manipulate the % complete based on what you know to be true when your costs are lagging behind.  You do have to use the Options Update feature whenever you open the window to get the data to refresh, otherwise the budget, costs to date will be whatever you saw the last time you opened that job record.  

Children