Change Order Tracking

When we self preform change order work on a project, is there a way to tract those labor and material costs separately without having to create a phase or use a new cost code? I've tried both of those methods and I'm just not loving either way.  

Parents Reply Children
  • in reply to Char DeLange

    Hi Char!

    Yes, that is how we currently handle it. But, when an architect wants to track the changes on a separate line on the pay app, the only way I can differentiate between material for the original scope and material in the same cost code for a change, is to note that its for a change in the description of the material invoice entry. 

    I was hoping someone had figured out a way to "post" self preformed time and material to a change order, similar to how we post to a subcontract or purchase order. 

    I hope that makes sense...?