Newbie here.

Setting up Job Cost from older system; looking for suggestions on best way to number jobs.  Currently use xx-yyzz (x=year, y=next job in sequence, zz=additional letters for exdtras, separate costs tracking).

Job number also integral part of purchasing; job no is beginng of the PO number.

Suggestions much appreciated, thank you!

John

Parents
  • 0

    We use year and job #.  19-0123.  We set up a separate Cost Code for Extras.  Actually we use a Cost Code Groups and then break it down.  8-000 Extras (nothing is put to the 8-000 code because that is group name)   8-100 concrete extra  8-200 milling extras   8-300 paving extras. etc.  