Job Status

SOLVED

The 3 Basic Job Statuses are not enough for me.  Everytime I run a WIP, etc. it pulls everything that is In Progress.  But if I close the job (during closeout for example) then we cannot continue to enter costs, etc. I'm guessing there is no way to add another Job Status in 300 CRE

Parents
  • 0
    SUGGESTED

    Hi, just wanted to let you know our current work around for this.  In Job Cost > Setup Jobs, there are customizable fields on the "General" tab.  We have edited one of those fields to be "Pending CL" (for pending closure).  This way we can run a list of open jobs and add the column for Pending CL to the query and see which jobs should not have time entered against them during the close-out period.  Hope this helps you.  (But you're right, another status would be ideal!)

Reply
  • 0
    SUGGESTED

    Hi, just wanted to let you know our current work around for this.  In Job Cost > Setup Jobs, there are customizable fields on the "General" tab.  We have edited one of those fields to be "Pending CL" (for pending closure).  This way we can run a list of open jobs and add the column for Pending CL to the query and see which jobs should not have time entered against them during the close-out period.  Hope this helps you.  (But you're right, another status would be ideal!)

Children