• Labor And Rate Tables Not Transferring

    My database that was setup when I bought the system had the pricing in units, an earlier question on here was answered by the Gary gentleman that seems to answer most of these. I tried to create a new database so I could select the crew pricing in hours…
  • Project Management Revise contract amount discrepency

    Intermittently, when I'm Saving or Printing a Change Order and I have "Revise contract amount" checked, the contract amount will not revise to match the Change Order in Contracts/Job Costs. If I was to use Sage Estimating to modify an estimate and select…
  • I'm noticing that when I go back to certain takeoffs in estimating that the bid item's data will be deleted even after saving... why??

    I'm noticing that when I go back to certain takeoffs in estimating that the bid item's data will be deleted even after saving... why?? I go back to an estimate, expecting to see the final bid amount, but often it is lower than what I remember. When…
  • Take-offs

    When we go back to take-offs, our bid items were deleted. This has begun recently with no change in personnel access and already running the current version of Sage. Any suggestions?
  • Updating material prices in the database editor.

    Can anyone tell me why some some material prices in the database editor are displayed in red?
  • Unable to retrieve data for estimate

    Error retrieving data for an estimate. Error: "Error Staging Data No data was returned by Sage Estimating. This could be caused if the estimate you selected is currently open (locked) in Sage Estimating. Close the estimate and then try again…
  • WBS Codes are not defined

    I work for a company that uses Estimating and I recently helped them upgrade to 19.12. I don't work in Estimating but help them with their IT needs. All of the sudden when they create a new estimate they're receiving the message: the following database…