Payroll - Job Costing

SUGGESTED

If anyone can offer suggestions on this I would greatly appreciate it. We issue payroll at our company bi-weekly. After payroll has been processed (we use an outside payroll company), I then come into sage and enter all the employees hours and job cost their time to the various jobs and work orders (we have the service module - but its the same thing as just posting it to a job if you don't have that). The issue I am running into is that we cannot see the labor until after two weeks. That is a serious lag for us when we want to review work orders that are completed in just one day. Does anyone have any better way of posting payroll to the various jobs or job costing their payroll? I thought that maybe the daily payroll would help, but again, it doesn't actually job cost anything. Nothing actually gets job costed until I hit the final compute. Help??

I tried calling support and she recommended making sure we input the hours the employee is supposed to work when we enter the work order but again that doesn't help us. We want to track how much time they actually are spending out there and see which jobs we are making or losing money, etc. So seeing the real costs.

Parents
  • 0

    Run a trial compute on the records you have then create a query in 5-2-2 to reflect the unposted labor and add it as a supplement to your job cost read-out.  

  • 0 in reply to JoshH

    We are having the same issue - our payroll is bi-weekly so we can't see accurate job profit reports until the final compute.  Our Consultant told us that the Service Module would fix this, so we paid for the Service Module - only to find that it just records total hours - it doesn't differentiate between regular and overtime (???)... so that doesn't help us at all.  

    We can't wait the full two weeks to run job reports.   Any other suggestions?

  • 0 in reply to smaris
    SUGGESTED

    Have you looked at report 11-1-2-#91 estimated Work Order Profitability?  

    I just ran it on the Sample Company and it pulled an estimated labor cost value based on the technician's time put on the work order.    #72 is editable so you could add a burden rate using a calculated field.

  • 0 in reply to Char DeLange
    SUGGESTED

    For construction projects (not service work orders) you can use the cost to complete menu 6-8 for hours or costs to complete reports which will add burden to the payroll costs.

  • 0 in reply to Char DeLange

    If I enter within a workorder just to see the reports then I will still have to go back and re-enter everything into payroll - since when the Workorder is imported there is no differentiation between regular and overtime hours.  

    If I make invoices using T&M billing (to ensure that the time gets tracked and marked as billed), then we have to wait the full two weeks until the final compute is done before we can create the invoice.

Reply
  • 0 in reply to Char DeLange

    If I enter within a workorder just to see the reports then I will still have to go back and re-enter everything into payroll - since when the Workorder is imported there is no differentiation between regular and overtime hours.  

    If I make invoices using T&M billing (to ensure that the time gets tracked and marked as billed), then we have to wait the full two weeks until the final compute is done before we can create the invoice.