Trying to delete a commitment change order that has been approved and it is now grayed out. Is there a way to change from approved to pending or even deleting it? Thanks.
Hi Christina1,
Job Cost commitment change orders cannot be deleted or changed after they are approved. New change orders would need to be entered to reverse the original change, or to correct it.
One of the benefits of Project Management is to be able to edit or delete approved change orders and commitment change orders. It may be work exploring adding that back in just for that purpose.
I am very curious as to what is project management? Is that an add on program. Because I am forever changing reversing change orders it seems like.
I am very curious as to what is project management? Is that an add on program. Because I am forever changing reversing change orders it seems like.
Project Management is one of the Sage 300 CRE modules. It's used for created and tracking Submittals, RFIs, Transmittals, and other construction documents. It also has a more flexible change management system where you can make corrections to approved change orders on the fly, without having to undo and redo the work.
If you would like more information or a quote, PM me your account number.
Thanks!
*Community Hub is the new name for Sage City