We are trying to get lines of labor into our T&M cost based billing jobs. We enter the labor through the JC Direct Costs table using category (L). The transaction date is the date worked, the accounting date being end of the work month. We are trying this for both November and December, both months still open. When we go into the cost based billing table, the lines for those entries are not there (Generating and re-generating WIP) . The hrs are showing on JC Exec summary though. We have checked to see if anything is hung up and not posted. We did a test by entering equipment (category E) this way and those costs went through no problem.
We are fairly knowledgeable with both JC and Cost based billings but not PR and are now completely out of ideas.
Thanks in advance.