Hello guys,
I hope you are well.
I made some researches but surprisingly, i didn't find any answer.
In the table PORDERQ, do you know, how the field RETRCPDAT is populated and what its purpose ?
Many thanks for your help,
Hello guys,
I hope you are well.
I made some researches but surprisingly, i didn't find any answer.
In the table PORDERQ, do you know, how the field RETRCPDAT is populated and what its purpose ?
Many thanks for your help,
Hi,
The only information I found was at HELP at V12 where it says:
Planned Due Date:
[M: POH2] RETRCPDAT (NOL)
[M: POI1] RETRCPDAT (NOL)
This information is associated with the Entry point LTIPRICE: Calculation of the planned reception date with the price list deadline, TRTACHTAR source.
Best Regards,
GF
Hello Marcow,
How can I check if the RETRCPDAT comes from MRP calculations or Sales order delivery date ?
When I analyse the RETRCPDAT data, for the same product, the difference in days is the same between the RETRCPDAT and the order date for all the POs. Therefore I get the impression that the RETRCPDAT is Order date + a lead time which means it should come from MRP calculations. If it's true, how can I change the product's lead time ?
Hello Nicolasson,
RETRCPDAT comes from Sales order when you are using back to back order fonctionality
MRP define RETRCPDAT and then with LT (Purchase LT on ITEM-SITE table) the system assign order date (Order date = RETRCPDAT-LT). in ORDERS table, type="POS" you will find STRDAT = ORDER date ENDDAT = expect receipt date and MRPDAT = Requirement Date (if empty ENDDAT=requirement date)