Demand Horizon and MRP

Does anyone have a better definition of the demand horizon than what has been in the training material ?

Also does anyone know what the affects of having the demand horizon set to 0 means for a manufactured good?

Thank you! 

Parents
  • 0

    The demand horizon (field FOH on product-site) defines when a forecast is defined as expired by MRP / MPS processing (when setup HORDEM on the MRP /MPS requirement parameter is on). The whole benefit is to define how the system identifies a forecast that is obviously incorrect. 

    For instance, should you replenish your stock (purchased, manufactured or subcontracted product) if you have a forecast for tomorrow but no sales order? By setting your demand horizon (and combined with HORDEM = ticked) to 1 week, you will ensure that MRP will consider for the next week only sales document (SOF and SOP) but not forecasts (SOS). 

    Another example is a forecast that is below the actual sales: in 2 weeks time (after he demand forecast) you have 100 as forecast (SOS) but an actual sales of 150 (SOF). MRP / MPS will consider that the actual need to fulfilled is MAX (SOS; SOP+SOF) so 150 in this case. 

    I hope this is clearer now.

Reply
  • 0

    The demand horizon (field FOH on product-site) defines when a forecast is defined as expired by MRP / MPS processing (when setup HORDEM on the MRP /MPS requirement parameter is on). The whole benefit is to define how the system identifies a forecast that is obviously incorrect. 

    For instance, should you replenish your stock (purchased, manufactured or subcontracted product) if you have a forecast for tomorrow but no sales order? By setting your demand horizon (and combined with HORDEM = ticked) to 1 week, you will ensure that MRP will consider for the next week only sales document (SOF and SOP) but not forecasts (SOS). 

    Another example is a forecast that is below the actual sales: in 2 weeks time (after he demand forecast) you have 100 as forecast (SOS) but an actual sales of 150 (SOF). MRP / MPS will consider that the actual need to fulfilled is MAX (SOS; SOP+SOF) so 150 in this case. 

    I hope this is clearer now.