MRP Settings have the load calculation at 26 weeks.
The production lead time is set to Routing/Product Lead time
From what I can see in the load graphs, I only see load for 6 months.
and from the MRP results, I can see that the routing is used for the first 6 months and then the product-site lead time after that
If I change the load calculation in the MRP settings to say 52 weeks, does this mean that we will:
- use the routing duration in the MRP to set the start and dates
- will then be able to view the load for the next year
then also, does that mean that the product-site lead times are never used to calculate load on a work center ?