Does anyone know if there is a way in Sage to force the line numbering between the Req and the PO to be consistent? Our Purchasing department would really like them to be consistent if possible.

Parents
  • 0

    Your problem is that X3 has the capability to combine lines from different requisitions onto a PO, and that the requisition itself is not limited to a single supplier. All  of those functions would need to be controlled. If you are just needing it for reporting purposes there will be data in the PO lines that will link back to a requisition and I would think that the traceability functionality would also allow that.

Reply
  • 0

    Your problem is that X3 has the capability to combine lines from different requisitions onto a PO, and that the requisition itself is not limited to a single supplier. All  of those functions would need to be controlled. If you are just needing it for reporting purposes there will be data in the PO lines that will link back to a requisition and I would think that the traceability functionality would also allow that.

Children