How to complete a part receipted GRV

SOLVED

A GRV has been processed for the PO and some lines were missed.

How to complete the GRV, not sure if it will duplicate the lines already receipted.

Parents
  • 0
    verified answer

    Hi Musa

    This is quite easy to answer.

    Evolution allows for a user to partially process a Purchase Order e.g. only certain lines gets GRV'ed

    To process the rest of the currently unprocessed PO lines, do the following:

    1. On the Purchase Order Maintenance screen, select the options marked below

    2. Find the and open the relevant PO and then process the rest of the lines. 

    Kind Regards

    Bennie 

Reply
  • 0
    verified answer

    Hi Musa

    This is quite easy to answer.

    Evolution allows for a user to partially process a Purchase Order e.g. only certain lines gets GRV'ed

    To process the rest of the currently unprocessed PO lines, do the following:

    1. On the Purchase Order Maintenance screen, select the options marked below

    2. Find the and open the relevant PO and then process the rest of the lines. 

    Kind Regards

    Bennie 

Children