Scenario:
We have a work order that runs over 2 days, over 3 shifts.
At the end of each shift, the consumption/tracking are handed over to the next shift.
**Reintegration/stock return is done for pallets that were not fully consumed, but will be consumed by the next shift.
Is it possible to:
To not track quantities when producing(short release).. and instead of doing a reintegration... be able to enter the consumed amount of a pallet, leaving the pallet with its remaining qty.
Then a label can be reprinted and placed on the pallet.
Overall... we want to avoid re-integration/return and track components after production, not as we consume.