Hi,

We both purchase and manufacture (it is a by product) the same product, however the WO costing always defaults to the Purchased cost, is there any around this to force the manufactured product to use the standard cost rather than the cost of the last purchase?

Thanks

Top Replies

Parents Reply
  • 0 in reply to Dan Dyson
    SUGGESTED

    Hi 

    In the actual cost calculation on the release product, the material cost comes from the valuation method set on the product-site.

    If you want the actual cost to pick-up standard cost for your component, you would need to set all components with STD valuation method:

    This change affects the stock valuation process, hence be sure to test / approve the impact on your GL.

    Note: by-product component type (See the Production BOM definition) are always valued using standard cost. We face a product limit here: we cannot, without customization, value the by-product stock using actual cost tracked on the work order.